The
first level of the helix is complete in this late January view,
except for the addition of feeder terminal blocks. There will be one
on each straight section which feeds all tracks. |
In late January Walt helped me add the second deck support stud
walls for the Glenrock side of the layout (in the background) and
for the Laurel peninsula. These walls are also support the framing
for the backdrops. Here we clamped a half-sheet of plywood to the
Laurel studs to get an idea of how the backdrop will divide the
room. |
This
photo is just a detail of how we built the support stud walls. The
bottom plate is a pressure-treated 2X4, used to resist the moisture
inherent in contact with a cement floor. The studs were set into
place and screwed to the bottom plate toe-nail fashion. |
|
February |
With
the addition of the support stud wall, it became possible to start
adding track that is dependent on exactly where those walls went.
Here we see the Lander Branch track being installed behind the
helix. Helix construction temporarily stopped so that I could reach
over it to work on the Lander track installation, if necessary.
Turns out I didn't have to do that - I laid the track on the roadbed
prior to attaching the roadbed to the risers, and just slid the
whole assembly around as needed to gain access to lay the track. |
We're
looking at the Lander Branch from the opposite direction of the
above photo, more or less. The roadbed still isn't attached to the
risers in this shot - in fact, the risers behind the helix and above
the NP mainline are yet to be installed. |
The
helix as it stands on 8 February. You can see the test train with
the locos nose (a BLI Heavy Mike) at the current end of track. The
loco seems to perform very well on the helix grade - it pulls 14
cars (counting the caboose) up the grade, and will start on the
grade, without slipping. And this loco doesn't have a traction-tired
driver yet. With the traction tire installed, I'm anticipating 20-22
car trains to move up the helix with no difficulty (I was a little
apprehensive about the pulling power of steamers on the grade). |
|
March |
The
helix as of March first. The first one and one-half tiers are laid,
marking this as about 25% of the way up at end-of-track. |
Two
weeks later - March 15th. The next semi-circle has been lowered and
connected, and trackwork can now progress. |
In
late February and early March I installed the lower deck portion of
the Frannie Cutoff. The inner curve here is the cutoff in work.
Around the top of the curves to the right of the photo is the double
crossover at the west end of Laurel. Finally that last turnout tail
has somewhere to go! |
The
curves out of the west end of Laurel, this time to the bottom left
out of the frame, with the Frannie track now complete. |
The
roadbed and some track have been installed where the Cody branch
leaves the helix for Cody. From this point in the helix upwards, the
helix is four-track. |
The
installed section of the Cody branch leading from the helix towards
Cody. The roadbed is left curving back to the helix for now just to
support the free end. the curve will be cut off later so that the
branch will parallel the helix. I'm standing in the middle of the
someday Cody refinery. |
In
late March the Glenrock benchwork near the helix looked like this.
The under-construction roadbed crossing over the NP Minneapolis yard
throat is part of the Wyoming Mainline that runs from the helix to
Thermopolis well behind the camera. The upper track on the left is
the Cody branch shown above. |
A
few days later gives us this longer view, showing a substantial part
of the helix-to-Thermopolis roadbed is now complete. |
|
April |
It's
now mid-April, and I'm re-grading the helix-to-Thermopolis line. You
can see that some of the track on the line is installed, but it
turns out the level isn't sensitive enough to provide an accurate
grade indication with just the bubble. So I set up a laser level to
check and adjust the grade. It took quite a bit of adjusting. I knew
what the rise should be over a four-foot distance, so I set a block
of that height under the lower end of a four-foot level and adjusted
the self-leveling laser to catch the top edge of the level. I
adjusted the risers until the laser beam caught the entire top of
the level, screwed the riser in place, then moved on to the next
section. It worked great! The white background is .080 inch thick
sheet styrene. Backdrops for the layout will be made of this stuff. |
In
this late April shot towards the helix, track has been laid on the
helix-Thermopolis roadbed, most of the way down the Glenrock
benchwork. That's the track with the tanker train on it. As it
leaves the picture to the right, that train enters the helix at the
lowest level and starts it's climb to the top deck. |
A
closer view of the helix-Thermopolis track, showing where it enters
the helix at the right. The stub of subroadbed in front of the
Thermopolis track will take the line into Glenrock siding. |
The
upper train is on the completed lower level of the Frannie Cutoff.
It's on the temporary track that will connect it to Glenrock and
allow trains to run from the NP Mainline onto the lower deck Wyoming
Mainline trackage. Once the upper deck has been completed to Orin,
this connection will be removed and the track connected to the helix
for the trip to the top deck. |
An
overall view of most of the layout as of April 23rd. The elevated
line to the left is the Frannie Cutoff, and in the extreme
background you can see the Thermopolis-to-helix track (the one with
the train on it). |
|
May |
Glenrock
siding subroadbed installation has begun in this May 3rd photo! Just
behind me as I'm taking this picture will be Thermopolis.
Because Glenrock siding sits
above Minneapolis staging yard I couldn't just plant risers to
support Glenrock siding. So I wound up building three-piece framing
to act as risers. |
Here's a view from the opposite direction, from behind the helix.
This view won't be seen when the layout is a little farther along.
When the Lander branch and
Thermopolis-to-helix tracks have progressed around the corner and
onto the Thermopolis benchwork, the backdrop will be mounted in its
permanent position, to the left of the Thermopolis track in this
photo. |
Meanwhile
helix construction has progressed somewhat, though slowly due to all
the other work going on. Track is now laid until the second tier is
almost complete. The fourth track, the one coming in from the back
to be the outermost helix track, is the connection from Cody. |
|
August |
In
early July I attended the National Train Show in Philadelphia. While
there I stopped by the FastTracks booth and was so impressed by what
I saw that I bought a turnout fabrication kit from them. This is the
first turnout I built using it - a #6 code 83 left-hand turnout.
This will go at the east end of Glenrock siding when I get the track
there. I thought my turout building days were over! |
Glenrock
roadbed, with the helix in the background, as of mid-August. The
track coming off the helix to the left mid-way up is the branch to
Cody. |
The helix as of mid-August. Three
loops are now complete - Three to go. |
Power
strips feeding the helix. Each tier has two strips feeding each
track - one on each straight section. Although the strips are
installed, the power isn't being fed by these right now. It's coming
from the alligator clips you see on the bottom terminal strip. One
all the helix track is laid, the power will be hooked up completely. |
A
closeup of one of the power strips. |
|
September |
Early
in the month. The helix is now 3 1/2 loops finished - 2 1/2 to go.
Thanks to Walt's help, this half loop was done in only about two
weeks. My goal is to complete the helix by Thanksgiving - one day
shy of a year since it was started. |
Test
trains on the helix, parked one level below where trackwork is being
done. |
Here's
an overall view of the helix as of September 4. It's starting to
look kind of impressive! I added a shop light in the center of the
helix in June or July - I got tired of having to move around a
little work light constantly. |
|
November |
The
night before Thanksgiving - the helix is complete! Construction
started one day shy of one year ago. |
That's
a whole lotta track! The helix gobbled up 175-185 pieces (I'm not
totally sure) of Atlas code 100 flex track. |
Powering
the monster - this one of the two power distribution nodes for the
helix. There's one just like it on the other side of the helix.
Power comes in from the main bus, and is distributed through the
smaller-diameter sub-feeders to the track feeder strips at each tier
of the helix. |
|
December |
|
In late December I installed the
turntable (a 90' Walthers) at Laurel, and ran enough track to
actually turn an engine! The track leading to the turntable now will
be the outbound track. The inbound track will come straight in from
this view. |